Schedule is weather dependent and subject to change at the last minute. Should weather or dump site not be suitable for pipe installation pipe crew will transition to Hydrant Locations or all work could be canceled due to weather. Should weather not allow pipe install, Crew 1 will be forced to move to hydrant installs. Should Crew 1 need to complete hydrant installs this will accelerate the hydrant schedule.

During the water system improvements there will be water service interruptions. The water service interruptions will take place between 9AM and 5PM unless there is an unforeseen problem. In this event the contractor and borough will take the steps to notify and keep the residents updated.

Crew 1 Pipe Jan. 15-19
Locations: North Ave. & 3rd Street to North Ave. & 6th Street

Crew 2 Jan. 17-23 9 Qty. Hydrant Locations It is estimated to complete 2 hydrant locations per day/crew
THIS IS THE ORDER IN WHICH CREW WILL COMPLETE THE HYDRANT INSTALLS:

  • Kellinger Drive
  • Kellinger Drive & Jones Ave.
  • Charles Street
  • Carle Street & McKee Ave.
  • Straube Ave.
  • Dorothea Street & Hartman Way
  • Neely Street & Perkins Way
  • Schiller Street
  • Schiller Street & Market Street